Project Timelines

May 2023

Commenced outreach and engagement with the City of Pickering, indigenous communities, and area residents

September 21, 2023, 6-8 pm

Public community meeting: Chestnut Hill Recreation Complex 1867 Valley Farm Road Pickering, Ontario L1V 3Y7 

December 12, 2023

IESO LT1 RFP submission deadline

Spring 2024

IESO LT1 RFP contract award

2024-2025

Engineering, Design, & Approvals. Obtain local and provincial permits, complete interconnection assessment and agreements with transmitter and system operator

2026

Anticipated construction start

2027

Target Commercial Operation Date 

 

Local Outreach

Plus Power has been developing Trillium since 2023 with a focus on meeting the capacity needs of Ontario’s electricity system and the customers it serves.  We have been engaging with all local stakeholders regarding the Trillium project and will continue to provide updates, obtain feedback, and answer questions throughout the development process. Updates regarding community outreach will be posted here as the project progresses. We are committed to working with all local stakeholders to ensure a successful project.

Read our Community and Indigenous Engagement Plan

Community Benefits

Trillium will be a good neighbor and a valuable asset to the surrounding community for decades to come. The Project will provide necessary capacity to the province with nearly zero polluting emissions. Additionally, Trillium will have little impact on neighboring businesses or the community at large; as a static facility, the Project generates insignificant traffic and creates minimal demand for municipal services. Significant project benefits to the community include:

  • High-paying construction and O&M jobs

  • Enhanced resiliency from a new, state-of-the-art power resource

  • Expanded property tax base for the local district